Lan County: Foundry Industrial Park will form a casting capacity of 300,000 tons

Project is the carrier of economic and social development, and also an effective starting point for transformation and development. On the basis of coordinating the prevention and control of the epidemic, Lan County took the lead in launching the construction of 81 key projects with a total investment of 14 billion yuan this year, and pressed the “fast-forward button” to seize projects in the new year and promote transformation and development. .

The construction site of the standardized workshop construction of the Lanxian Economic and Technological Development Zone Foundry Industrial Park upgrading project. After more than a year of intensive construction, the five workshops covering an area of ​​50,000 square meters have entered the final stage of leveling and pouring. This is also the key project with the largest investment in Lanxian Economic and Technological Development Zone since last year. Development has laid a solid foundation.

The upgrading project of the foundry industrial park is a key construction project launched by Lanxian Economic and Technological Development Zone on the basis of continuously optimizing the business environment to create a green intelligent foundry base integrating production, education and research, and to provide enterprises in the park with complete production and operation sites. . The total investment of the project is 550 million yuan, covering an area of ​​250,000 square meters. 10 fully enclosed steel structure standard workshops are newly built, and supporting production, living, scientific research and other areas. So far, 5 standardized workshops have been built. After the completion of the project, a casting capacity of 300,000 tons will be formed, which will further enhance the level of intelligent equipment in Lanxian Economic and Technological Development Zone, and comprehensively improve the casting equipment, casting materials, and casting processes.

Lan Huijun, Deputy Director of the Construction and Planning Department of Lanxian Economic and Technological Development Zone: After the project is completed, it can be used as the first position for the development zone to attract investment, create a high-quality and convenient production and living platform for the introduction of leading foundry enterprises, and create an upgraded version of the development zone. , to provide strong support for the high-quality development of Lanxian Economic and Technological Development Zone in an all-round way.

The alkaline pellet production line project with an annual output of 2 million tons is a key upgrade and transformation project for green iron ore mining and comprehensive utilization of resources launched by Taiyuan Iron and Steel Group Lanxian Mining Co., Ltd. since last year. Since the resumption of work in February this year, more than 200 construction workers have overcome the impact of the epidemic and worked overtime to promote the project construction. So far, a total investment of 130 million yuan has been completed. After the basic pellet production line is completed and put into operation, it can not only realize comprehensive and efficient utilization of the high-sulfur magnetic ore powder produced by the enterprise, but also greatly reduce the production cost and total pollutant discharge of the enterprise, and realize the clean and efficient production of the enterprise.

[Same period]Zhang Zhigang, deputy director of the Engineering Management Department of Shanxi Taigang Engineering Technology Co., Ltd.: After our project is completed and put into operation, the alkaline pellets with an annual output of 2 million tons can completely replace imported lump ore, and the blast furnace can reduce sintered ore by 900,000 tons per year. tons, greatly reducing the production cost and increasing the efficiency of the enterprise by 261 million yuan per year. At the same time, the total emission of pollutants has been greatly reduced, reducing particulate matter by 24 tons, sulfur dioxide by 84 tons, and nitrogen oxides by 120 tons each year, injecting strong vigor and vitality into the development of high-end foundry clusters in Lanxian County.

This year, Lanxian firmly established the concept of focusing on projects as focusing on development, coordinated epidemic prevention and control and economic and social development, and took the lead in pressing the “fast-forward button” for project construction in the city. A few days ago, the construction of 81 key projects with a total investment of 14 billion yuan started, of which 53 are new projects and 28 are continued projects, covering infrastructure, social security, ecological environmental protection, agricultural industry, new energy industry, industrial enterprises, Seven sections of cultural tourism. In order to promote the early effect of the project and win the “double victory” of epidemic prevention and control and economic and social development, Lanxian has implemented the “six one” project promotion mechanism and the “four one” assessment method for the landing project, and made every effort to promote the smooth construction of the project.

[Concurrent period]Zu Liangping, director of the Lanxian Key Project Promotion Center: We implement the “six one” project promotion mechanism of “one project, one leader, one plan, one team, one fund, and one catch” for the landing projects. . At the same time, the “Four Ones” supervision and scheduling assessment methods are implemented, adopting the methods of supervision once a month, scheduling once a season, observation once every six months, and assessment once a year, to track the nanny service throughout the project to ensure that the project can be put into production as soon as possible and take effect as soon as possible. .