The main body of the welding workshop of Chery Automobile Qingdao Base Project (Phase I) is capped, and the equipment will enter the site in April

The main body of the welding workshop of Chery Automobile Qingdao Base Project (Phase I) is capped, and the equipment will enter the site in April

On the morning of December 21, 2021, with the precise installation of the last purlin in place, the main structure of the welding workshop of Chery Automobile Qingdao Base Project (Phase I) undertaken by China Construction Eighth Engineering Bureau was successfully capped. After the completion of the project, it will add new kinetic energy to build the highland of the national new energy automobile industry.

Since the first hoisting of the steel column in the welding production area on October 8, 2021, the project construction team has increased the investment in machinery and equipment, created conditions to rush to the work surface, and completed the main capping of the steel structure of the welding workshop 10 days in advance. It is understood that, in view of the characteristics of plant sealing, floor flatness, and high structural safety, the construction unit China Construction Eighth Engineering Development and Construction Company adopted large-area floor laser leveling technology to achieve any acceptance requirements for workshop floor flatness 2 The height error within meters should be kept within ±2 mm, and the height error within 10 meters should be controlled within ±5 mm.

At present, the stamping workshop, painting workshop and assembly workshop are also under construction. The welding workshop is under construction of steel structure fireproof coating, wall keel and floor engineering; the stamping workshop (including parts library) is currently under construction of steel structure fireproof coating and Floor plain soil leveling and pressing work; the paint shop is under construction on the main body of the first floor, and 50% of the main body of the first floor has been completed; 68% of the main steel column hoisting of the general assembly workshop has been completed, and the main steel rescue frame hoisting has begun. It is planned that the main construction of all workshops will be completed in January 2022, and the process equipment will begin to enter the site in April.

It is reported that the project is located to the east of Xinshui 1st Road, Qingdao Automobile Industry New Town, Jimo District, Qingdao City, to the west of Buxi Road, and to the south of Jiefang 3rd Road. The steel structure construction scope mainly includes welding production area and stamping production area, with a total steel consumption of about 8,300. Ton. The welding production area is a rectangular layout as a whole. The main structure is truss + portal frame structure, including lower steel columns, upper truss structure and portal frame beam structure. The total length is 278m and the total width is 204m. After the project is completed, It will add new kinetic energy to build the highland of the national new energy automobile industry.

Assistant General Manager Wang Weiwei of Chery Automobile Co., Ltd., Bai Youan, Secretary of Disciplinary Work Committee of Qingdao Automobile Industry New City Management Committee, Cui Mingshou, Chairman of Qingdao Chengxin Holding Group Co., Ltd., Sun Baorui, Vice President of China Automotive Industry Engineering Co., Ltd., Qingdao Huapeng Engineering Ding Hui, President of Consulting Group Co., Ltd., Chen Chenglin, deputy general manager of China Construction Eighth Engineering Bureau Development and Construction Company, and Yang Zhikai, general manager of China Construction Eighth Engineering Development and Construction Company First Branch, attended the topping ceremony.